wiregrass ranch high school

Florida Building Commissioning for Wire Grass High School

Project Details

  • Owner/ Client: Pasco County Schools

  • Project Size: 60,000 sq. ft.

  • Architect: Holmes Hepner & Associates

  • Engineer: Lyle Engineering Group

  • CxA Firm: SITACx

  • HVAC Commisioning Firm: SITA

  • Construction Management: Beck

Project Description

SITA provided comprehensive Commissioning and TAB services for the HVAC mechanical systems, which included functional performance test of the HVAC controls system to ensure proper operation. SITA's hands-on approach to commissioning, as well as the complete understanding of the HVAC systems during the TAB portion of the project, allowed a complete beginning-to-end evaluation of the HVAC systems. This unique combined Commissioning and TAB service provided by our firm was cost effective for the owner and ensured proper operation of the HVAC systems.

Similar Projects